CASE STUDIES
Client
William Grants & Sons Distillers
Location
Dufftown, Scotland
​
Client Enquiry
Valley and gable gutter replacements on 2no warehouses.
Duration
8 weeks - September 2025
Services Provided
-
Survey and Report
-
Professional Advice & Specific Solutions for the client to choose from
-
Preparation of the area
-
Waterproofing system applied
-
Edge Corrosion system applied
-
Comprehensive Completion Report
​
Challenges
-
Distillary still operational: Work had to be planned to minimise disruption and keep access safe.
-
Weather: Rain caused the issue, but repairs also needed a suitable dry window for safe application.
-
No Hot Work permitted due to nature of the business.
​
Solutions
-
Site survey & Diagnostic report : Roof inspection and damage assessment.
-
Preparation: Cleaned and prepared surfaces to ensure proper adhesion.
-
Waterproofing repair: Applied a waterproofing system to seal roof penetrations and prevent further ingress.
-
Edge Corrosion system applied to seal the edges of the roof to prevent futher corrosion
-
Photographic Breakdown & Completion Report provided to Client Representative.

Client
GENCO
​
Location
Bracknell, Berkshire
​
Client Enquiry
Defective movement-expansion joint causing damage to warehouse plant machinery.
​
Duration
5 days - January 2026
​
Services Provided
-
Site Visit and work recommendation proposal with detailed site report drawings and solutions provided.
-
Preparation of the area
-
Installation of Metal Joints
-
Application of sealing system around the joints
-
Comprehensive Completion Report
​
Challenges
-
Warehouses keep operational: Works had to be phased to keep routes open, maintain safety, and minimise disruption to day-to-day movements.
-
Trip hazard at the warehouse joint: The uneven interface between the two warehouse floors created a clear H&S risk for pedestrians and trolleys.
-
Working inside temperature-controlled environment ( 5 °C Chiller chamber )
​
Solutions
-
Site survey & work assessment prior to work and location proposal.
-
Preparation: Cleaned and prepared the area to achieve proper adhesion and a durable finish.
-
Metal joint installation + sealing: Installed metal joints and applied a sealing system around them to lock the detail in place and reduce future movement-related issues.
-
Photographic Breakdown & Completion Report provided to Client Representative on completion.

Client
Squerryes Winery
Location
Westernham, Kent
​
Client Enquiry
Water damage to the Winery Restaurant following the rainfall.
​
Duration
2 days - works completed January 2026
​
Services Provided
-
Site survey & Diagnostic report : Roof inspection and damage assessment.
-
Work recommendation proposal supported with tailor made solutions.
-
Preparation of the area causing issue
-
Waterproofing system applied
-
Comprehensive Completion Report
​
Challenges
-
Winery still operational: Work had to be planned to minimise disruption and keep access safe.
-
Weather: Rain caused the issue, but repairs also needed a suitable dry window for safe application.
-
Leak tracing: Water ingress can travel, so the true source (around roof penetrations) had to be accurately identified.
​
Solutions
-
Site survey & Diagnostic report : Roof inspection and damage assessment.
-
Preparation: Cleaned and prepared surfaces to ensure proper adhesion.
-
Waterproofing repair: Applied a waterproofing system to seal roof penetrations and prevent further ingress.
-
Photographic Breakdown & Completion Report provided to Client Representative.

Client
Clarion Housing
Location
Borehamwood, Hertfordshire
​
Client Enquiry
Water damage to the Winery Restaurant following the rainfall.
​
Duration
4 days – works completed December 2025
​
Services Provided
-
Site survey & Diagnostic report with damage assessment.
-
Work recommendation proposal supported with tailor made solution.
-
Fit and supply scheduled visit and arrangement of decant for duration of works
-
Implementation of Health and Safety measures and Risk Assessment Audit.
​
Challenges
-
Structural works relating removal of complete to two-storey house.
-
Decanting process agreement and precise work programme.
-
Tailor made solution with design of brand-new stair construction
-
Health and Safety considerations
​
Solutions
-
Complete strip out and site clearance.
-
Fit and supply of brand-new staircase wooden construction.
-
Complete decoration works and making good on completion.
-
Resident feedback and Satisfaction Form signed off.
-
Photographic Breakdown & Completion Report provided to Client Representative.