CASE STUDIES
Client
CBRE
Location
The National Exhibition Centre (NEC) Birmingham.
Client Enquiry
Issues with water ingress to 12no Sub-Stations located on the flat roof to Plaza Hall
Duration
3 weeks – April 2026
Services Provided
-
Site Survey and Report
-
Reinforced waterproofing UV stable coating system and specification proposal.
-
Deep clean and decontamination throughout.
-
Cold liquid applied – no hot works
-
Installation of the bespoke 2mm steel details to door and air vents
-
Installation of the heavy duty self-gripping metal reinforced PVC door seals to shuts and returns.
-
Replacement of weathered H&S signs and labels with rigid custom-made signs fitted on site.
Challenges
-
Weather dependent works
-
Location and restricted access to roof
-
Detail work customization and bespoke finish
Solutions
-
Site protection and proposal of reinforced waterproofing UV stable coating system to both horizontal and vertical areas.
-
Installation of custom-made metal flashing to all areas required.
-
Tailor made labelling and H&S signage to all Sub-Stations.
-
Photographic Breakdown & Completion Report provided to Client Representative.

_edited.jpg)
Client
CBRE
Location
BT (British Telecom)
Client Enquiry
Resurfacing works to Residential & Business use driveway due to Health and Safety
Duration
5 days - Preparation: 3 days; Resurfacing: 2 days
Services Provided
-
Site inspection / survey and quotation.
-
Full site Set up and Site manager on site.
-
Site preparation including vegetation, tree stump and roots removal and making good.
-
CCTV drainage inspection and drain unblock.
-
Installation of private access sign at entrance to road
-
Complete Resurfacing works to residential and business driveway to approx. 250m2
Challenges
-
Weather permitting works.
-
Restricted access , narrow road with limited movement options.
-
Traffic managements and marshalling measures in place.
-
Private driveway with residential access.
-
HGV and specialist plant machinery in operation
Solutions
-
Full site inspection, survey and quotation carried out to plan works around restricted access.
-
Site set up with dedicated site manager to oversee traffic management and marshalling for HGVs and plant.
-
CCTV drainage inspection and drain unblock completed alongside site preparation.
-
Private access sign installed at road entrance to manage vehicle movements.
-
Works programmed with weather-permitting flexibility throughout.
Location
Multi Storey Car - Bordon,Hampshire
Client Enquiry
Car Park Waterproofing system application to 2170m2 including ramps.
Duration
4 weeks
Services Provided
-
Site Survey and Daily Site Quality Assurance Reporting.
-
Deck preparation prior to system application
-
Application of Triflex Deckfloor system throughout.
-
Crack banding and scratch coat repairs
-
Detail works to steel column upstands and reinforced fleece installation to rainwater system and outlets.
Challenges
-
Weather factors e.g. wind, rain.
-
Extra protection to the deck edges prior to system installation
-
Plenty of detail work
Solutions
-
Adjusted the programme to include weekend working and extended shifts to offset weather-related delays, ensuring the project remained on schedule despite rain
-
Implemented additional temporary protection measures to the deck edges ahead of system installation, safeguarding the substrate and reducing the risk of damage or contamination
-
Allocated additional resource and supervision time to detail-heavy areas (upstands, penetrations, drainage outlets), ensuring quality and consistency of workmanship without compromising the overall programme
_edited.png)

Client
GENCO
Location
Bracknell, Berkshire
Client Enquiry
Defective movement-expansion joint causing damage to warehouse plant machinery.
Duration
5 days - January 2026
Services Provided
-
Site Visit and work recommendation proposal with detailed site report drawings and solutions provided.
-
Preparation of the area
-
Installation of Metal Joints
-
Application of sealing system around the joints
-
Comprehensive Completion Report
Challenges
-
Warehouses keep operational: Works had to be phased to keep routes open, maintain safety, and minimise disruption to day-to-day movements.
-
Trip hazard at the warehouse joint: The uneven interface between the two warehouse floors created a clear H&S risk for pedestrians and trolleys.
-
Working inside temperature-controlled environment ( 5 °C Chiller chamber )
Solutions
-
Site survey & work assessment prior to work and location proposal.
-
Preparation: Cleaned and prepared the area to achieve proper adhesion and a durable finish.
-
Metal joint installation + sealing: Installed metal joints and applied a sealing system around them to lock the detail in place and reduce future movement-related issues.
-
Photographic Breakdown & Completion Report provided to Client Representative on completion.
Client
William Grants & Sons Distillers
Location
Dufftown, Scotland
Client Enquiry
Valley and gable gutter replacements on 2no warehouses.
Duration
8 weeks - September 2025
Services Provided
-
Survey and Report
-
Professional Advice & Specific Solutions for the client to choose from
-
Preparation of the area
-
Waterproofing system applied
-
Edge Corrosion system applied
-
Comprehensive Completion Report
Challenges
-
Distillary still operational: Work had to be planned to minimise disruption and keep access safe.
-
Weather: Rain caused the issue, but repairs also needed a suitable dry window for safe application.
-
No Hot Work permitted due to nature of the business.
Solutions
-
Site survey & Diagnostic report : Roof inspection and damage assessment.
-
Preparation: Cleaned and prepared surfaces to ensure proper adhesion.
-
Waterproofing repair: Applied a waterproofing system to seal roof penetrations and prevent further ingress.
-
Edge Corrosion system applied to seal the edges of the roof to prevent futher corrosion
-
Photographic Breakdown & Completion Report provided to Client Representative.